The latest update on the A16 Springfield Roundabout.
What we achieved in February
- Continued earthworks in the northeast and southwest corners
- Finished kerbing and drainage in the northeast and southwest corners
- Constructed new carriageway on the northeast and southwest corners
- Installed street lighting ducting
- Started topsoiling the verges
What’s happening in March
- Complete earthworks and verges in the northeast and southwest
- Switch over to working in the northwest and southeast areas of site
- Start earthworks and drainage in the northwest and southeast corners
- Start BT diversion in the southeast corner
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- N/A