The latest update on the Grantham Southern Relief Road.
What we achieved in January
Phase Three
- West side of site – continued steelwork assembly / installed permanent formwork and cantilever formwork
- East side of site – second base pour for east concrete abutment / concrete south wing wall base / reinforce and shuttering to north wingwall base / connect temporary decking to Pier 5
What's happening in February
Phase Three
- West side of site – reinforce fixing on bridge deck / installation of cantilever formwork
- East side of site – concrete east abutment main base / reinforce and shuttering to north wingwall base / concrete north wingwall base / being backfilling east abutment base / connect temporary structure decking and reinforcement to Pier 5 / shutting, concrete pier base and reinforcement to Pier 6 base
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A