The latest update on the A16 Springfield Roundabout.
What we achieved in January
- Continued earthworks in southwest corner of the roundabout
- Started Kerbing, drainage, and earthworks in the northeast and southwest corner of the roundabout
- Excavated and started construction of new widened sections of northeast and southwest corners of carriageway foundation layers
- Completed BT diversionary works in northeast corner of project
- Completed headwalls in the northeast and southwest corner
What’s happening in February
- Complete construction of carriageway foundation in northwest and southeast corners
- Complete kerbing and drainage in northwest and southeast corners
- Start installing street lighting ducting and boxes
- Finish earthworks in the northeast and southwest corners
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- N/A