Latest updates on the A16 Levelling Up Fund improvements.
What we achieved in December
- Completed relocation of the 33kV electricity cables in the southwest corner
- Installed temporary footway and started BT diversionary works to the northeast corner
- Carried out site clearance in the southwest, northeast and west corners of the scheme
- Completed drainage in the northeast corner
What’s happening in January
- Completed earthworks in southwest corner of the roundabout
- Kerbing, drainage, and earthworks in the northeast and southwest corner of the roundabout
- Carriageway foundation layers of new widened sections of northeast and southwest corner excavated and constructed
- Complete BT diversionary works in northeast corner of project
- Construct headwalls in the northeast and southwest corner
Current/ongoing traffic restrictions and closures
- 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits maintained
- Ongoing narrowed roundabout lanes
Upcoming traffic restrictions and closures
- N/A