Latest updates for Spalding Western Relief Road.
What we achieved in October/November/December
- Completed prep work so deck works can begin
- Completed landscaping activities, including grass seeding and bulb planting
- Installed the bridge beams onto the piers and abutments
- Completed east and west diaphragm pours
- Completed two deck pours
- Completed ducting at Junction H
- Installed badger culvert
What's happening in January/February/March
- Complete settlement of and continue surcharge removal at the west junction and low height embankment
- Install kerbing, drainage and street lighting at western junction
- Continue construction of retaining wall
- Continue construction of the bridge deck
- Complete remaining deck pours
Current/ongoing traffic restrictions and closures
- Closure of Two Plank Bridge and Blue Gowt Lane
Upcoming traffic restrictions and closures
- Closure of public right of way 15/1 and Two Plank Lane for bridge footpath construction – starting 12th February until Summer 2024