The latest updates for the Grantham Southern Relief Road.
What we achieved in December
Phase Three
- West side of site – completed steelwork assembly
- East side of site – Pier 6 blinding (base layer of weak concrete or sand) / east abutment reinforcement fixing and shuttering to initial pour / Pier 5 temporary structure foundations and construction
What's happening in January
Phase Three
- West side of site – install permanent and cantilever formwork / reinforce fixing on bridge deck
- East side of site – Pier 6 reinforcement / east abutment concrete works / reinforcement to wingwall bases / Pier 5 reinforcement and temporary structure decking
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A