What we achieved in October

Phase Three

  • West side of site – cast bridge launch foundations for western foundation
  • East side of site – east abutment excavation and pile cropping / Pier 5 backfill and concrete works / Pier 6 piling works

What's happening in November

Phase Three

  • West side of site – complete trestle launch foundations / begin assembling steelwork
  • East side of site – east abutment excavation and pile cropping / Pier 5 concrete works / Pier 6 piling works

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A