What we achieved in October
Phase Three
- West side of site – cast bridge launch foundations for western foundation
- East side of site – east abutment excavation and pile cropping / Pier 5 backfill and concrete works / Pier 6 piling works
What's happening in November
Phase Three
- West side of site – complete trestle launch foundations / begin assembling steelwork
- East side of site – east abutment excavation and pile cropping / Pier 5 concrete works / Pier 6 piling works
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A