What we achieved in October
- Completed works for A16/Marsh Lane roundabout southeastern widening, including drainage works, laying of new kerbs and bituminous carriageway base layers, installation of street lighting and Openreach utility diversion
- Commenced construction of the roundabout central island on A16
- Continued shared-use cycleway/footway works along Marsh Lane
- Continued carriageway reconstruction works at Marsh Lane
- Commissioned the permanent traffic signals at the Marsh Lane / Wyberton Low Road crossroads
- Started A16 carriageway surfacing works
What’s happening in November
- Continue carriageway reconstruction works at Marsh Lane and A16
- Continue construction of shared-use cycleway/footway along Marsh Lane
- Begin footway works on London Road
Current/ongoing traffic restrictions and closures
- 24/7 lane closures on A16
- 24/7 temporary traffic signals along Marsh Lane, east of crossroads
- Night-time road closures of A16, 7pm to 7am, weekday evenings only, until mid-November
- Weekend temporary traffic signals at A16/Marsh Lane roundabout until mid-November
- Weekend temporary traffic signals and HGV convoy system at Marsh Lane until mid-November
- Weekend closures of Wyberton Low Road at Marsh Lane crossroads until mid-November
Upcoming traffic restrictions and closures
- Southbound road closure on London Road once A16 works completed