Grantham Southern Relief Road October 2023 update

Image of latest works from Grantham Southern Relief Road

Latest updates for Grantham Southern Relief Road.

What we achieved in September

Phase Three:

  • West side of site – continued removal of the surcharge to the west abutment
  • East side of site – piling east abutment / Pier 5 base pours

What's happening in October

Phase Three:

  • West side of site – cast bridge launch foundations for western foundation
  • East side of site – east abutment excavation and pile cropping / Pier 5 backfill and concrete works / Pier 6 piling works

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd October 2023