Latest updates for Grantham Southern Relief Road.
What we achieved in September
Phase Three:
- West side of site – continued removal of the surcharge to the west abutment
- East side of site – piling east abutment / Pier 5 base pours
What's happening in October
Phase Three:
- West side of site – cast bridge launch foundations for western foundation
- East side of site – east abutment excavation and pile cropping / Pier 5 backfill and concrete works / Pier 6 piling works
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A