An update on what was completed during August 2023.
What we achieved in August
Phase Three
- West side of site – started removal of the surcharge to the west abutment
- East side of site – piling east abutment / Pier 5 blinding and formwork, reinforcement and concrete works
What's happening in September
Phase Three
- West side of site – continue removal of the surcharge to the west abutment
- East side of site – piling east abutment / Pier 5 base pours
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A