Grantham Southern Relief Road September 2023 update

A birds eye view of the progress on the Grantham Southern Relief Road

An update on what was completed during August 2023.

What we achieved in August

Phase Three

  • West side of site – started removal of the surcharge to the west abutment
  • East side of site – piling east abutment / Pier 5 blinding and formwork, reinforcement and concrete works

What's happening in September

Phase Three

  • West side of site – continue removal of the surcharge to the west abutment
  • East side of site – piling east abutment / Pier 5 base pours

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 4th September 2023