Bridge works and surfacing remedial works have been completed at the new A1 bridge.
What we achieved in July
Phase Two
- Carried out bridge joint remedial works and surfacing remedial works at the new A1 bridge
Phase Three
- West side of site – completed ‘pull test’ on Pier 1
- East side of site – excavation and pile cropping to Pier 5 / continued piling to the east abutment
What's happening in August
Phase Three
- West side of site – begin removal of the surcharge to the west abutment
- East side of site – piling east abutment / Pier 5 blinding and formwork, reinforcement and concrete works
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.