Grantham Southern Relief Road August 2023 update

An overhead view of the future Grantham Southern Relief Road

Bridge works and surfacing remedial works have been completed at the new A1 bridge.

What we achieved in July

Phase Two

  • Carried out bridge joint remedial works and surfacing remedial works at the new A1 bridge

Phase Three

  • West side of site – completed ‘pull test’ on Pier 1
  • East side of site –  excavation and pile cropping to Pier 5 / continued piling to the east abutment

What's happening in August

Phase Three

  • West side of site – begin removal of the surcharge to the west abutment
  • East side of site – piling east abutment / Pier 5 blinding and formwork, reinforcement and concrete works

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.

Published: 2nd August 2023