This month bridge joint remedial works and surfacing will commence at the new A1 bridge.
What we achieved in June
Phase Three
- West side of site – completed topsoiling and finishing works near Pond B
- East side of site – completed Pier 5 piling / completed white lining
What's happening in July
Phase Two
- Bridge joint remedial works and surfacing remedial works at the new A1 bridge
Phase Three
- East side of site – excavation and pile cropping to Pier 5 / continue piling to the east abutment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- Night-time closure of northbound A1 / Monday 17 July for up to five evenings, 8pm to 6am (bridge joint works and sections of resurfacing)
- Night-time southbound A1 lane closure and slip road closure / Monday 17 July for up to five evenings, 8pm to 6am