Grantham Southern Relief Road May update

A birds eye view of the progress of Grantham Southern Relief Road

This month we'll be installing signage and continuing piling work.

What we achieved in April

Phase Three

  • East side of side – continue piling to the east abutment / construct Pier 5 piling platform

What's happening in May

Phase Two

  • Installation of signage under night-time southbound A1 lane closure

Phase Three

  • East side of side – complete Pier 5 piling platform / continue piling to the east abutment and move to Pier 5 once platform is constructed / complete white lining to eastern side of site / open Whalebone Lane to traffic

Current/ongoing traffic restrictions and closures

  • Overnight A1 southbound lane closure; Wednesday 9 May for two evenings, 8pm to 6am
  • Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
  • Whalebone Lane closed until Friday 5 May

Upcoming traffic restrictions and closures

  • N/A

For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.

Published: 3rd May 2023