This month we'll be installing signage and continuing piling work.
What we achieved in April
Phase Three
- East side of side – continue piling to the east abutment / construct Pier 5 piling platform
What's happening in May
Phase Two
- Installation of signage under night-time southbound A1 lane closure
Phase Three
- East side of side – complete Pier 5 piling platform / continue piling to the east abutment and move to Pier 5 once platform is constructed / complete white lining to eastern side of site / open Whalebone Lane to traffic
Current/ongoing traffic restrictions and closures
- Overnight A1 southbound lane closure; Wednesday 9 May for two evenings, 8pm to 6am
- Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
- Whalebone Lane closed until Friday 5 May
Upcoming traffic restrictions and closures
- N/A
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.