Grantham Southern Relief Road April update

An overhead view of the progress of Grantham Southern Relief Road

Phase three is progressing well, with splitter islands at the development roundabout completed.

What we achieved in March

Phase Three

  • West side of site – completed drainage to Pond B
  • East side of side – completed splitter islands at development roundabout / completed hydroseeding at eastern side of project / install main steelwork to Pier 4 / begin finishing works to development roundabout area verges / began construction of working platforms for piling new elements of bridge / began white lining along the newly-built road

What's happening in April

Phase Three

  • East side of side – continue piling to the east abutment / construct Pier 5 piling platform / complete white lining to eastern side of site

Current/ongoing traffic restrictions and closures

  • Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
  • Whalebone Lane closed

Upcoming traffic restrictions and closures

  • N/A

For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.

Published: 3rd April 2023