Final set of major A17 improvements near Sleaford planned for next month

Diversion route a17

Works to reconstruct the section of A17 between Byards Leap and Holdingham Roundabout will start on in April.

Cllr Richard Davies, executive member for highways, said: "Following on from last year’s improvements to the A17 between Beckingham and Leadenham, we’ll be heading back to the A17 this spring for a final set of works – this time to rebuild the carriageway between Byards Leap and Holdingham Roundabout.

“This section is also showing signs of deterioration, so we’re taking the opportunity now to fully rebuild it using nearly 15,000 tonnes of stone and tarmac.”

Dates and timeframes

Monday 10 April for up to ten weeks (subject to weather)

Traffic management

Night-time road closure on the A17 from 7pm to 6am (weekday evenings only)

Please note that some weekend working will be required from 7pm Friday night until 6am on the following Monday morning. The proposed weekend is currently Friday 21 to Monday 24 April.

Location of works

Between Byards Leap and Holdingham Roundabout on the A17

Diversion route

Diversion route A17

A17 diversion: via the A46 to the Lincoln Eastern Bypass / A15 / Holdingham Roundabout

Main Street (heading south from the A17) at North Rauceby / Tom Lane / Rauceby Drove / A153 Grantham Road / A15

Rauceby Lane (heading north from the A17): College Road / B1429 Sleaford Road / A15

Cllr Davies added: "We'll be doing everything we can to keep disruption to a minimum throughout these major A17 improvements, including maintaining access for emergency services where it’s safe to do so and carrying the works out as quickly and efficiently as possible.

“In the meantime, I want to thank everyone in advance for their patience.”

For up-to-date information about this and other roadworks, visit www.lincolnshire.gov.uk/roadworks

Published: 28th March 2023