Grantham Southern Relief Road March update

GSRR March update 2023

Phase three is progressing well, with pier works completed on the west side and surfacing on the east side.

What we achieved in February

Phase Three

  • West side of site – completed pier infill works at Piers 1 and 2 / continued drainage works near the west embankment and Pond B
  • East side of side – completed surfacing between Whalebone Lane and development roundabout / continued verge finishes to the development roundabout area / installed main steelwork to Pier 4

What's happening in March

Phase Three

  • West side of site – complete drainage works at Pond B
  • East side of side – complete splitter islands at development roundabout / complete hydroseeding / construct working platforms for piling the new elements / lay white lining

Current/ongoing traffic restrictions and closures

  • Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
  • Whalebone Lane closed

Upcoming traffic restrictions and closures

  • N/A