Grantham Southern Relief Road September update

Grantham Southern Relief Road September update

Works at Somerby Hill Roundabout complete

What we achieved in August

Phase Three

  • West side of site – pier 2 bases concreted / pier 3 bases reinforcement fixed and concreted
  • East side of side – complete works at Somerby Hill roundabout / install filter drains & road box and began infiltration trenches between Whalebone Lane and development / begin next set of ground investigation works / started piling works for pier 4

What's happening in September

Phase Three

  • West side of site – pier 3 bases concreted / pier 2 and 3 upstands concreted
  • East side of side – excavate plug of earth at Whalebone Lane / continue road box & surfacing and complete infiltration trenches between Whalebone Lane and development / complete pier 4 piling / excavate pier 4 cofferdam

Current/ongoing traffic restrictions and closures

  • Ongoing lane closures on the B1174 roundabout until the end of the scheme
  • Whalebone Lane fully closed
  • Temporary lane restrictions as needed at Somerby Hill Roundabout

Upcoming traffic restrictions and closures

  • N/A

For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.