1. For each of the past five years (2019-2024) how much did the council spend on fixing potholes?

2. And for each of the past five years (2019-2024) how many reports of potholes did the council receive?

3. Please could you also let me know how many the council repaired per year for the same time period?

Decision

Data is unavailable for potholes repaired prior to 2020 because Lincolnshire County Council (LCC) entered into a new Contract in April 2020 which allowed better recording of the number of specific jobs that were being completed. Prior to this 2020 contract, multiple potholes were completed and reported within one job, hence there is no way to provide an acceptable approximate figure. E.g., one job may have related to one, or many (possibly over a hundred) potholes.

 

1. LCC do not calculate the cost of repairs specifically allocated to potholes each year. There are several reasons for this; operationally it offers little value to spend time trying to assign costs at this level given the number of repairs undertaken per year but also there are a number of financial difficulties of trying to assign costs of materials and items of plant which are easily identified on a gang basis but further dividing these to specific repair type leads to inaccuracies.

 

2. See the table below.

 

3. See the table below.

 

Fiscal Year

Potholes Reported

Potholes Repaired

2019/2020

14509

Unavailable

2020/2021

11544

33638

2021/2022

12499

37722

2022/2023

12262

32274

2023/2024

19699

36476

 

​Please note, the number of potholes repaired in the above table, relates specifically to pothole jobs raised. However, this does not include additional potholes that would have been repaired through other additional works that were carried out by LCC on the carriageways during each of the years. E.g. Whole carriageway resurfacing works, carriageway patching and other carriageway minor works.

Reference number
10843249
Date request received
24 October 2024
Date of decision
21 November 2024