- Description of works
- Carriageway reconstruction works and footway resurfacing.
- Affected streets
-
Affected streets Unique street reference number Grid reference start Grid reference end Sea Lane 12611002 X552379 Y380445 X552718 Y380835 College Row 12653892 X552312 Y380563 X552421 Y380518 Roman Bank 12642887 X552421 Y380518 X553258 Y379910 Huttoft Bank 12648545 X553258 Y379910 X553783 Y378640 Roman Bank 12635107 X553783 Y378640 X555515 Y374925 Anderby Road 12610171 X555515 Y374925 X556162 Y373217 St Leonards Drive 12610208 X556162 Y373217 X556085 Y373099 - Expected commencement date of works
- 16 September 2024
- Expected completion date of works
- 28 February 2025
- Length of restriction
- Three years