1. The work Lincolnshire County Council is currently planning to undertake on Sutterton Drove this year are as follows.

• Estimated Target including fee - £158,000 including all traffic management costs.

• Area planned on being surfaced – 4,475 sq.m.

• Price per square metre (sq.m) - £35.31.

• Planned depth of reconstruction is 125mm, which is recycling 75mm and adding in 50mm of new material

• The whole area will then have one layer of surface dressing added immediately and an additional layer added in 2025, which will increase the overall thickness when completed.