Highway Development Control Services - Find a freedom of information request

Request

1. The total number of outstanding Section 278 and Section 38 works applications currently under your authority's review. 

2. The average or approximate processing times for Section 278 and Section 38 works applications, including the time taken for approvals. 

3. The average or approximate approval rates for Section 278 and Section 38 works applications in the last 12 months. 

4. The contact details (names, positions, and email addresses) of key personnel responsible for managing Section 278 and Section 38 works within your authority. 

5. Details of the fees and charges associated with Section 278 and Section 38 works approvals. 

6. Any available performance metrics related to Section 278 and Section 38 works, such as processing times, compliance rates, and customer satisfaction levels. 

7. Summary/bullet point information about any challenges faced by your authority in managing Section 278 and Section 38 works. 

Decision

1. 597.

2. Not recorded.

3. Not recorded.

4. DevelopmentManagement@lincolnshire.gov.uk. 01522 782070.

5. S278

Up-front fee - £5000.

Inspection Fee - 15% of bond value (minus up-front fee).

Land dedication - £650. Legal agreement - £180.

Commuted Sum - Specific to agreement.

S38

Up-front fee - £1320.

Development Road Fee - 8% of bond value (minus up-front fee).

Land dedication - £650. Legal agreement - £180.

Commuted Sum - Specific to agreement.

6. Not recorded.

7. Not Recorded.

Reference number
7476149
Date request received
26 July 2023
Date of decision
18 August 2023