- Request
-
1) in connection with the A16 Levelling Up Fund improvements I would like to see the feasibility report for the A16/Station Road junction at Kirton.
- Decision
-
Although a feasibility report was commenced and significant work was input into its development, it was clear that the options available to site a signalised junction improvement scheme within the existing highway boundary was limited to just one scenario.
Once this was known the project moved straight into detailed design so not to continue expending fees on the inevitable outcome.
Therefore, as the feasibility was not finalised, although all the data to inform the outcome was completed and valid, there is nothing formal to share other than the summarised findings which are already contained on the Lincolnshire County Council webpage.
- Reference number
- FOI 4680161
- Date request received
- 25/07/22
- Date of decision
- 08/08/22