Major Works to Resolve the Sinking Boston Road South Road in Holbeach - Find a freedom of information request

Request

Over the last 48 months major works to resolve the sinking Boston Road South road in Holbeach.

Please provide the following information:

1. The number of man hours spent on carrying the above work and the total expenditure, including materials spent to date to carry out this work.

Decision

Total expenditure: £184828.13.

Total man hours: 559.

Further information is attached.

If you would like to see a copy of the attachment please request it from CustomerInformationService@lincolnshire.gov.uk quoting the reference 3378305 .

Reference number
3378305
Date request received
15 February 2022
Date of decision
25 February 2022