- Request
-
I am requesting information relating to road / highway projects (e.g. roundabout improvements, new roads and junctions, major road resurfacing) funded or contributed to by your council from its capital budget and budgeted to cost over £500,000 or more.
1. I require data relating to any applicable projects carried out during the tax periods of 2017-18, 2018-19 and 2019-present date.
Of such projects, please provide the following information:
- Project name or description (e.g. Bell Lane roundabout improvements, M1 Junction XX works)
- Start date
- Planned delivery date
- Actual delivery date
- Planned budget
- Actual spend
- Decision
-
- A15 / A158 Wragby Road, Lincoln PRN
900k
Finishes Aug 19
- Sleaford Bank Slip
2.1m
Completed end July 18
- A46 Nettleham PRN
700k
Complete Mar 19
- A1500 Tillbridge Lane PRN
550k
Finishes Aug 19
- A16 Louth bypass PRN
600k
Completed June 18
- A158 Rand PRN
830k
Finished May 19
- A153 Horncastle PRN
700k
Finished Mar 19
- B1225 Ludford PRN
800k
Finished Apr19
- Woodhall Spa PRN
900k
Completed Oct 18
- Grantham Southern Relief Road (Phase1, Phase 2 and Phase 3)
Start date – September 2015
Planned delivery date – January 2023
Actual delivery date – not completed
Planned budget - £102m
- Reference number
- FOI0357
- Date request received
- 18 July 2019
- Date of decision
- 12 August 2019