Design and materials of external walls
Regulation 5 of the Fire Safety (England) Regulations 2022 require Responsible Persons of high-rise residential buildings to prepare a record of the design of the external walls and share it with their local fire and rescue service.
The purpose of providing this information is to assist with operational pre-planning and to provide information that will be of value to responding crews at the time of a fire.
As well as providing details of the materials used in the wall construction, Responsible Persons will also be required to provide information on the level of risk of fire spread that the external wall structure poses, and any steps that have been taken to mitigate these risks.
Responsible Persons should complete the notification of external wall construction form to provide the fire and rescue service with the necessary information required by the regulations.