Lincoln Eastern Bypass update – New Greetwell Road roundabout opens

Greetwell roundabout opening

The new 50-metre long, 53-tonne pedestrian and cycle bridge was raised into place on Wednesday 13 November.

What we achieved in December

  • Laid footpath surfacing at Hawthorn Road
  • Opened new Greetwell Road roundabout up following essential surfacing and lighting works
  • Continued drainage works between Washingborough Road and Greetwell Road
  • Completed surfacing between Sleaford Road to Lincoln Road
  • Completed bridge deck works for Hawthorn Road footbridge
  • Continued construction of River Witham Viaduct, including laying deck formwork and beginning installation of deck rebar
  • Constructed bank seats for South Delph footbridge
  • Continued construction of Heighington Road bridge, including deck waterproofing, drainage installation and fitting steel parapets
  • Progressed wing wall construction for Lincoln Road underpass
  • Continued abutment and wing wall works for Bloxholm Lane footbridge
  • Continued post-excavation archaeological reporting

What's happening in January

  •  Install fencing along Hawthorn Road footpath
  • Begin filter drains installation between Sleaford Road to Lincoln Road
  • Start construction of bases for Greetwell footbridge
  • Continue deck and wing wall construction, along with grouting the permanent bearings for the River Witham Viaduct
  • Continue construction of South Delph footbridge, including preparing for delivery of the bridge deck
  • Carry out essential kerbing and surfacing works to new Heighington Road bridge and re-open Heighington Road
  • Complete wing wall construction and waterproofing for Lincoln Road underpass
  • Continue abutment and wing wall works for Bloxholm Lane footbridge
  • Continue post-excavation archaeological reporting

Upcoming traffic restrictions and closures

  • Full 24/7 closure of Hawthorn Road from Monday 27 January
  • Full 24/7 closure of Washingborough Road starting Monday 17 February

Current/ongoing traffic restrictions and closures

  • Temporary speed restrictions on Washingborough Road, Greetwell Road, Lincoln Road, Sleaford Road and Hawthorn Road
  • Temporary traffic signals on Hawthorn Road and Washingborough Road to allow safe access for construction vehicles and machinery
  • Temporary 200m path diversion on the Sustrans route along the River Witham
  • Full 24/7 closure of Heighington Road until the end of January 2020
  • Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane

For the latest news on the Lincoln Eastern Bypass, visit www.lincolnshire.gov.uk/leb.

Published: 16th January 2020