Grantham Southern Relief Road May 2024 update

An image of the progress on the GSRR

The latest update on the Grantham Southern Relief Road.

What we achieved in April

Phase Three

  • West side of site – started installing Pier 3 stabilising working platforms
  • East side of site – concrete main abutment wall / cast masking walls and bearing plinths to Pier 5 / add reinforcement and formwork to east abutment wall / complete backfilling to Pier 6 base

What's happening in May

Phase Three

  • West side of site – complete install of Pier 3 stabilising working platforms
  • East side of site – fix reinforcement and shuttering to wingwall 1 / first concrete pour for wingwall 1 / partially strip scaffolding from Pier 5

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd May 2024